3 1/2Million Dollar Contract
|
||||
![]() |
We installed 60,000 feet of duct, and 20-25 manholes, as well as 15KV cable with major electrical upgrade from 4,160 Volts to 13,200 Volts. This contract took approximately 1 year to complete, with a crew of 8-10 men on the jobsite throughout the duration of the contract. | |||
|
|
||||
|
©